Route 9, Section 25K & 1F

Client:
NJ Department of Transportation
(NJDOT)
Trenton, New Jersey

Location:
Sayreville and Woodbridge, New Jersey

Project Cost:
$57,943,720

Completion Date:
October, 2002

References:
Dave Lambert
NJDOT Project Manager
(609) 530-4235
Tony Bene
NJDOT Resident Engineer
(732) 308-4073

Project Details

Our Route 9 project over the Raritan River was the Company’s first Design Build project. The project involved the design and construction of a 4,400 foot long, 60 foot wide bridge spanning the Raritan River and adjacent land from Sayreville to Woodbridge, New Jersey. The bridge was constructed in tight quarters between two existing bridge structures, the existing Route 9 bridge to the east and the Garden State Parkway bridge to the west.

The four lane superstructure is 100 feet above the river surface at its highest point and consists of five continuous span units, four of which are made up of post tensioned, spliced, concrete girders with a structural concrete deck. The center unit, over the water, is a continuous steel structure with a structural concrete deck. The substructure is comprised of twenty-five piers and two abutments founded on a combination of friction and bearing piles. The abutment is poured in place concrete with special architectural features. Abutment retaining walls are precast T-Wall construction. To facilitate construction of the water piers, eleven temporary steel cofferdams were constructed. Pier caps consist of a mix of conventional and post tensioned integral pier caps, supported by twin concrete columns.

The project involved the reuse of excavated soils in accordance with an approved soil reuse plan and the implementation of a project Health and Safety Plan. Reconstruction and rephasing of the bridge approaches was also included in this contract. At the completion of this project all traffic from the existing Route 9 bridge was diverted to the new bridge and the existing bridge was taken out of service for renovation under a separate contract. The project was completed on time and under budget.